Source page: Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm · Original file: original.xlsx · Provenance: table (parsed deterministically)
Row 14
| Task ID | Task | System | Interval | Procedure or reference | Duration (h) | Crew | Notes |
|---|---|---|---|---|---|---|---|
| MP-HYD-01 | Hydraulic accumulator pre-charge check | Hydraulics | 12 months | LT-32 manual chapter 9 | 1.5 | 2 |