FICTIONAL SAMPLE - Contoso Renewables, Quellmoor Ridge Wind Farm and every organisation, person, product and value in this wiki are invented. Not for operational use.
This spreadsheet is the 2026 maintenance plan, issue 2 dated 2026-07-01, for Quellmoor Ridge Wind Farm. It contains a maintenance task catalogue, a per-turbine 2026 plan, oil sampling results, and a revision log.
Key facts
- The document is Maintenance plan 2026, issue 2 dated 2026-07-01, for Quellmoor Ridge Wind Farm.1
- The plan owner is Dario Penwarden, O&M Supervisor at Contoso Renewables.2
- The spreadsheet contains the Tasks, Plan 2026, Oil sampling, and Revision log sheets.3
- Issue 2 added task MP-GBX-07 for all turbines after INC-2026-006 and brought the WTG-02 endoscope inspection forward to July.4
- Gearbox oil sampling and laboratory analysis task MP-GBX-01 is scheduled every 6 months, with a duration field of 1 h and crew field of 1.5
- Gearbox oil filter element replacement task MP-GBX-02 uses part FGT-P-11872, is scheduled every 12 months, and references SOP-GBX-010.6
- Gearbox oil change task MP-GBX-03 for PWG 220 is scheduled every 5 years or on condition, references SOP-GBX-010 Rev. B, has a duration field of 6 h, and notes that the next planned changes start from 2030.7
- Vibration trend review task MP-GBX-06 is monthly, has a duration field of 0.5 h, and is noted as a remote review by the Reliability Engineer.8
- Oil cooler radiator cleaning and fan current check task MP-GBX-07 is scheduled every 6 months, references INC-2026-006 (D7), and was added in issue 2 on 2026-07-01.9
- Generator brush inspection task MP-GEN-01 is scheduled every 6 months and references WI-GEN-014.10
- Slip ring cleaning task MP-GEN-02 is scheduled every 12 months and references WI-GEN-014.11
- Pitch bearing bolt re-torque task MP-PIT-01 covers 100 % of bolts at 1,450 Nm, is scheduled every 12 months, and references SB-LWS-2025-11 Rev. A.12
- Blade drone inspection task MP-BLD-01 is scheduled every 12 months and is noted as a contractor task for Wingtip Blade Services.13
- Rescue kit inspection task MP-HSE-01 is scheduled every 6 months and references SOP-WAH-003 section 7.14
- Fall arrest rail and ladder inspection task MP-HSE-02 is scheduled every 12 months and references SOP-WAH-003.15
- In the Plan 2026 sheet, WTG-02 gearbox endoscope inspection task MP-GBX-04 is planned for 2026-07 and has status done at 2026-07-01.16
- WTG-07 oil sampling report TR-OA-2026-0614 recorded PWG 220 oil, Fe of 64 ppm, PQ index of 112, condition ALERT, and next sample due 2026-07-10 with resampling within 30 days.17
- Issue 1 was issued on 2025-12-15 and updated the oil sampling schedule for PWG 220 under MOC-2025-012 action 5.18
Contents
Tasks
The Tasks sheet is the task catalogue for the plan.3
It includes gearbox tasks for oil sampling, oil filter element replacement, oil change, endoscope inspection, visual inspection and leak check, vibration trend review, and oil cooler radiator cleaning with fan current check.567192089
It also includes generator brush inspection, slip ring cleaning, pitch bearing bolt re-torque, blade drone inspection, yaw brake pad inspection, hydraulic accumulator pre-charge check, rescue kit inspection, and fall arrest rail and ladder inspection.1011121321221415
The pitch bearing bolt re-torque task specifies 100 % of bolts and 1,450 Nm.12
Table t01 · sheet "Tasks", rows 1–16
| Row | Task ID | Task | System | Interval | Procedure or reference | Duration (h) | Crew | Notes |
|---|---|---|---|---|---|---|---|---|
| 2 | MP-GBX-01 | Gearbox oil sampling and laboratory analysis | Gearbox | 6 months | LWS-MM-GBX-32 section 4.4 | 1 | 1 | |
| 3 | MP-GBX-02 | Gearbox oil filter element replacement (FGT-P-11872) | Gearbox | 12 months | SOP-GBX-010 | 1.5 | 2 | |
| 4 | MP-GBX-03 | Gearbox oil change (PWG 220) | Gearbox | 5 years or on condition | SOP-GBX-010 Rev. B | 6 | 2 | Next planned changes from 2030 |
| 5 | MP-GBX-04 | Gearbox endoscope inspection | Gearbox | 24 months | LWS-MM-GBX-32 section 4.4 | 3 | 2 | |
| 6 | MP-GBX-05 | Gearbox visual inspection and leak check | Gearbox | 6 months | LWS-MM-GBX-32 section 4.4 | 1 | 2 | |
| 7 | MP-GBX-06 | Vibration trend review (condition monitoring) | Gearbox | monthly | LWS-MM-GBX-32 section 4.4 | 0.5 | 1 | Remote review by the Reliability Engineer |
| 8 | MP-GBX-07 | Oil cooler radiator cleaning and fan current check | Gearbox | 6 months | INC-2026-006 (D7) | 2 | 2 | Added in issue 2 (2026-07-01) |
| 9 | MP-GEN-01 | Generator brush inspection | Generator | 6 months | WI-GEN-014 | 1.5 | 2 | |
| 10 | MP-GEN-02 | Slip ring cleaning | Generator | 12 months | WI-GEN-014 | 2 | 2 | |
| 11 | MP-PIT-01 | Pitch bearing bolt re-torque, 100 % of bolts, 1,450 Nm | Pitch | 12 months | SB-LWS-2025-11 Rev. A | 8 | 2 | |
| 12 | MP-BLD-01 | Blade drone inspection | Rotor | 12 months | Wingtip Blade Services | 1 | 2 | Contractor |
| 13 | MP-YAW-01 | Yaw brake pad inspection | Yaw | 12 months | LT-32 manual chapter 7 | 2 | 2 | |
| 14 | MP-HYD-01 | Hydraulic accumulator pre-charge check | Hydraulics | 12 months | LT-32 manual chapter 9 | 1.5 | 2 | |
| 15 | MP-HSE-01 | Rescue kit inspection | Safety | 6 months | SOP-WAH-003 section 7 | 0.5 | 1 | |
| 16 | MP-HSE-02 | Fall arrest rail and ladder inspection | Safety | 12 months | SOP-WAH-003 | 1 | 2 |
Agents can query this table as t01 with the query_table tool.
Plan 2026
The Plan 2026 sheet gives the per-turbine plan and status at 2026-07-01.3
WTG-01 has MP-GBX-07 planned for 2026-07 and 2027-01 with status planned at 2026-07-01.23
WTG-02 has MP-GBX-04 planned for 2026-07 with status done at 2026-07-01.16
WTG-07 has MP-GBX-02 planned for 2026-07 with status planned, and MP-PIT-01 planned for 2026-09 with status planned.2425
WTG-12 has MP-GBX-02 planned for 2026-12, MP-PIT-01 planned for 2026-09, and MP-GBX-04 planned for 2026-10; each listed status is planned at 2026-07-01.262728
Table t02 · sheet "Plan 2026", rows 1–109
| Row | Turbine | Task ID | Planned months | Status at 2026-07-01 |
|---|---|---|---|---|
| 2 | WTG-01 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 3 | WTG-01 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 4 | WTG-01 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 5 | WTG-01 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 6 | WTG-01 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 7 | WTG-01 | MP-GBX-02 | 2026-01 | done |
| 8 | WTG-01 | MP-PIT-01 | 2026-05 | done |
| 9 | WTG-01 | MP-BLD-01 | 2026-05 | done |
| 10 | WTG-01 | MP-GBX-04 | 2027-04 | planned |
| 11 | WTG-02 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 12 | WTG-02 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 13 | WTG-02 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 14 | WTG-02 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 15 | WTG-02 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 16 | WTG-02 | MP-GBX-02 | 2026-02 | done |
| 17 | WTG-02 | MP-PIT-01 | 2026-05 | done |
| 18 | WTG-02 | MP-BLD-01 | 2026-05 | done |
| 19 | WTG-02 | MP-GBX-04 | 2026-07 | done |
| 20 | WTG-03 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 21 | WTG-03 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 22 | WTG-03 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 23 | WTG-03 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 24 | WTG-03 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 25 | WTG-03 | MP-GBX-02 | 2026-03 | done |
| 26 | WTG-03 | MP-PIT-01 | 2026-05 | done |
| 27 | WTG-03 | MP-BLD-01 | 2026-05 | done |
| 28 | WTG-03 | MP-GBX-04 | 2027-04 | planned |
| 29 | WTG-04 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 30 | WTG-04 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 31 | WTG-04 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 32 | WTG-04 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 33 | WTG-04 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 34 | WTG-04 | MP-GBX-02 | 2026-04 | done |
| 35 | WTG-04 | MP-PIT-01 | 2026-05 | done |
| 36 | WTG-04 | MP-BLD-01 | 2026-05 | done |
| 37 | WTG-04 | MP-GBX-04 | 2026-10 | planned |
| 38 | WTG-05 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 39 | WTG-05 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 40 | WTG-05 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 41 | WTG-05 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 42 | WTG-05 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 43 | WTG-05 | MP-GBX-02 | 2026-05 | done |
| 44 | WTG-05 | MP-PIT-01 | 2026-05 | done |
| 45 | WTG-05 | MP-BLD-01 | 2026-05 | done |
| 46 | WTG-05 | MP-GBX-04 | 2027-04 | planned |
| 47 | WTG-06 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 48 | WTG-06 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 49 | WTG-06 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 50 | WTG-06 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 51 | WTG-06 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 52 | WTG-06 | MP-GBX-02 | 2026-06 | done |
| 53 | WTG-06 | MP-PIT-01 | 2026-05 | done |
| 54 | WTG-06 | MP-BLD-01 | 2026-05 | done |
| 55 | WTG-06 | MP-GBX-04 | 2026-10 | planned |
| 56 | WTG-07 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 57 | WTG-07 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 58 | WTG-07 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 59 | WTG-07 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 60 | WTG-07 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 61 | WTG-07 | MP-GBX-02 | 2026-07 | planned |
| 62 | WTG-07 | MP-PIT-01 | 2026-09 | planned |
| 63 | WTG-07 | MP-BLD-01 | 2026-05 | done |
| 64 | WTG-07 | MP-GBX-04 | 2027-04 | planned |
| 65 | WTG-08 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 66 | WTG-08 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 67 | WTG-08 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 68 | WTG-08 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 69 | WTG-08 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 70 | WTG-08 | MP-GBX-02 | 2026-08 | planned |
| 71 | WTG-08 | MP-PIT-01 | 2026-09 | planned |
| 72 | WTG-08 | MP-BLD-01 | 2026-05 | done |
| 73 | WTG-08 | MP-GBX-04 | 2026-10 | planned |
| 74 | WTG-09 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 75 | WTG-09 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 76 | WTG-09 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 77 | WTG-09 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 78 | WTG-09 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 79 | WTG-09 | MP-GBX-02 | 2026-09 | planned |
| 80 | WTG-09 | MP-PIT-01 | 2026-09 | planned |
| 81 | WTG-09 | MP-BLD-01 | 2026-05 | done |
| 82 | WTG-09 | MP-GBX-04 | 2027-04 | planned |
| 83 | WTG-10 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 84 | WTG-10 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 85 | WTG-10 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 86 | WTG-10 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 87 | WTG-10 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 88 | WTG-10 | MP-GBX-02 | 2026-10 | planned |
| 89 | WTG-10 | MP-PIT-01 | 2026-09 | planned |
| 90 | WTG-10 | MP-BLD-01 | 2026-05 | done |
| 91 | WTG-10 | MP-GBX-04 | 2026-10 | planned |
| 92 | WTG-11 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 93 | WTG-11 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 94 | WTG-11 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 95 | WTG-11 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 96 | WTG-11 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 97 | WTG-11 | MP-GBX-02 | 2026-11 | planned |
| 98 | WTG-11 | MP-PIT-01 | 2026-09 | planned |
| 99 | WTG-11 | MP-BLD-01 | 2026-05 | done |
| 100 | WTG-11 | MP-GBX-04 | 2027-04 | planned |
| 101 | WTG-12 | MP-GBX-01 | 2026-06, 2026-12 | done |
| 102 | WTG-12 | MP-GBX-05 | 2026-03, 2026-09 | done |
| 103 | WTG-12 | MP-GBX-07 | 2026-07, 2027-01 | planned |
| 104 | WTG-12 | MP-GEN-01 | 2026-04, 2026-10 | done |
| 105 | WTG-12 | MP-HSE-01 | 2026-02, 2026-08 | done |
| 106 | WTG-12 | MP-GBX-02 | 2026-12 | planned |
| 107 | WTG-12 | MP-PIT-01 | 2026-09 | planned |
| 108 | WTG-12 | MP-BLD-01 | 2026-05 | done |
| 109 | WTG-12 | MP-GBX-04 | 2026-10 | planned |
Agents can query this table as t02 with the query_table tool.
Oil sampling
The Oil sampling sheet records per-turbine last sample date, report, oil, Fe (ppm), PQ index, condition, and next sample due.29
WTG-07 is the only highlighted exception in the key facts: its row shows report TR-OA-2026-0614, oil PWG 220, Fe 64, PQ index 112, condition ALERT, and next sample due 2026-07-10 with resampling within 30 days.17
WTG-01 through WTG-06 and WTG-08 through WTG-12 rows show condition NORMAL and next sample due 2026-12.2930313233343536373839
Table t03 · sheet "Oil sampling", rows 1–13
| Row | Turbine | Last sample | Report | Oil | Fe (ppm) | PQ index | Condition | Next sample due |
|---|---|---|---|---|---|---|---|---|
| 2 | WTG-01 | 2026-06-08 | TR-OA-2026-0603 | PWG 220 | 10 | 25 | NORMAL | 2026-12 |
| 3 | WTG-02 | 2026-06-08 | TR-OA-2026-0604 | PWG 220 | 27 | 22 | NORMAL | 2026-12 |
| 4 | WTG-03 | 2026-06-08 | TR-OA-2026-0605 | PWG 220 | 22 | 25 | NORMAL | 2026-12 |
| 5 | WTG-04 | 2026-06-09 | TR-OA-2026-0606 | PWG 220 | 27 | 22 | NORMAL | 2026-12 |
| 6 | WTG-05 | 2026-06-09 | TR-OA-2026-0607 | PWG 220 | 13 | 9 | NORMAL | 2026-12 |
| 7 | WTG-06 | 2026-06-09 | TR-OA-2026-0608 | PWG 220 | 24 | 12 | NORMAL | 2026-12 |
| 8 | WTG-07 | 2026-06-10 | TR-OA-2026-0614 | PWG 220 | 64 | 112 | ALERT | 2026-07-10 (resample within 30 days) |
| 9 | WTG-08 | 2026-06-10 | TR-OA-2026-0610 | PWG 220 | 27 | 17 | NORMAL | 2026-12 |
| 10 | WTG-09 | 2026-06-10 | TR-OA-2026-0611 | PWG 220 | 22 | 11 | NORMAL | 2026-12 |
| 11 | WTG-10 | 2026-06-11 | TR-OA-2026-0612 | PWG 220 | 14 | 26 | NORMAL | 2026-12 |
| 12 | WTG-11 | 2026-06-11 | TR-OA-2026-0613 | PWG 220 | 14 | 12 | NORMAL | 2026-12 |
| 13 | WTG-12 | 2026-06-11 | TR-OA-2026-0615 | PWG 220 | 25 | 26 | NORMAL | 2026-12 |
Agents can query this table as t03 with the query_table tool.
Revision log
Issue 1, dated 2025-12-15, issued Plan 2026 and updated the oil sampling schedule for PWG 220 under MOC-2025-012 action 5.18
Issue 2, dated 2026-07-01, added MP-GBX-07 for all turbines after INC-2026-006 and brought the WTG-02 endoscope inspection forward to July.4
Table t04 · sheet "Revision log", rows 1–3
| Row | Issue | Date | Change | Author |
|---|---|---|---|---|
| 2 | 1 | 2025-12-15 | Plan 2026 issued; oil sampling schedule updated for PWG 220 (MOC-2025-012 action 5). | Dario Penwarden |
| 3 | 2 | 2026-07-01 | Task MP-GBX-07 added for all turbines after INC-2026-006; WTG-02 endoscope brought forward to July. | Dario Penwarden |
Agents can query this table as t04 with the query_table tool.
About
The About sheet identifies the document as Maintenance plan 2026, issue 2 of 2026-07-01, for Quellmoor Ridge Wind Farm.1
The owner is Dario Penwarden, O&M Supervisor, Contoso Renewables.2
The document is marked fictional and not for operational use.40
Table t05 · sheet "About", rows 1–5
| Row | FICTIONAL - NOT FOR OPERATIONAL USE |
|---|---|
| 2 | Maintenance plan 2026, issue 2 of 2026-07-01, Quellmoor Ridge Wind Farm. |
| 3 | Owner: Dario Penwarden, O&M Supervisor, Contoso Renewables. |
| 4 | Sheets: Tasks (task catalogue), Plan 2026 (per turbine), Oil sampling, Revision log. |
| 5 | FICTIONAL - NOT FOR OPERATIONAL USE |
Agents can query this table as t05 with the query_table tool.
Figures
No figures were extracted from this document.
Related
- Assets: Quellmoor Ridge Wind Farm, WTG-01, WTG-02, WTG-03, WTG-04, WTG-05, WTG-06, WTG-07, WTG-08, WTG-09, WTG-10, WTG-11, WTG-12
- Components: gearbox, generator, generator brushes, hydraulic system, oil cooler, oil filter element, pitch bearing, pitch bearing bolts, rescue kit, rotor blade, slip ring, yaw system
- Spare part: FGT-P-11872
- Products: Litware LT-32, Proseware PWG 220
- Procedures: SOP-GBX-010 Gearbox oil change, SOP-WAH-003 Working at height and rescue, WI-GEN-014 Generator brush replacement
- Service bulletin: SB-LWS-2025-11 Pitch bearing bolt re-torque
- Organisations: Contoso Renewables, Wingtip Blade Services
- Topics: Blades, pitch bearings and main-component lifts, Gearbox lubrication and oil changes, Gearbox temperature, vibration and oil analysis, Generator brushes and electrical systems, Safety, isolation and work at height
Sources
Footnotes
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "About", row 2 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "About", row 3 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "About", row 4 · table ↩ ↩2 ↩3
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Revision log", row 3 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 2 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 3 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 4 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 7 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 8 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 9 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 10 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 11 · table ↩ ↩2 ↩3
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 12 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 15 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 16 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Plan 2026", row 19 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 8 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Revision log", row 2 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 5 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 6 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 13 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Tasks", row 14 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Plan 2026", row 4 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Plan 2026", row 61 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Plan 2026", row 62 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Plan 2026", row 106 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Plan 2026", row 107 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Plan 2026", row 109 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 2 · table ↩ ↩2
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 3 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 4 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 5 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 6 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 7 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 9 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 10 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 11 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 12 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "Oil sampling", row 13 · table ↩
-
Maintenance Plan 2026, Issue 2 — Quellmoor Ridge Wind Farm — sheet "About", row 5 · table ↩
Provenance badgestable values parsed deterministically from the cited table rows